Water Upgrade Project

Published: 20th July 2020

Monday 17th August, 2020 to Wednesday 9th December, 2020, inclusive.

Commencing on Monday 17th August, survey and construction teams will be establishing work sites in order to undertake the upgrade of the major water supply pipeline in Trunding.  The pipeline runs through Trunding from Central Avenue along York Road, Circular Way and Flinders Street to Duyfken Crescent. 

Works are scheduled to progress for eighteen weeks.  Planned commencement and completion dates for each section of the pipeline, as well as the survey and under-road boring tasks, are indicated on the image below.

Water upgrades